CSC constructed the Rashidiya station for the Oman Oil Company (OMCO) in Al Ahsa and equipped it to turnkey. The work included building and construction, mechanical, electrical and electronic works, infrastructure and finishes. The project duration is five months, and will be completed in 2024.
Gas stations
Al Rashidiya Station – OMCO, Al Ahsa
OMCO's Rashidiya station in Al-Ahsa was delivered ready for operation within five months.
Client
Oman Oil Company (OMCO)
sector
Gas stations
City
Al-Ahsa
Scope
Turnkey gas station
Status
Completed
Project Overview
Al Rashidiya Station - OMCO, Al Ahsa
Completed Scope
Building and construction works
Mechanical works
Electrical works
Electronic systems
Infrastructure
Finishes
Turn key
Key Construction Stages
Site and foundation works
Excavation, backfilling, canopy foundations, islands, tank networks and underground pipes.
Canopy and buildings
Installing the canopy structure and covering it with the customer’s identity, and implementing the service building and attached shops.
Squares and identity
Asphalt, concrete and drainage works, then signs, identity pole and lighting.
Tests and commissioning
Testing of tanks and safety systems before delivery for operation.
Quality and Testing
Testing the tightness of tanks and piping networks
Calibration of filling systems
Testing of fire and safety systems
Checking grounding and lightning rod
Testing the layout of the squares and their inclinations