CSC demolished the old tower station buildings and facilities, then rebuilt the station and its infrastructure for SASCO. The construction included fuel tanks, workshop buildings, a laundry, a supermarket, and a canopy, along with a chapel, an administration office, staff housing, and electrical and control rooms. We also carried out the finishing, mechanical and electrical works, advertising boards, then sidewalks, asphalt, yard planning and landscaping. The project duration is six months, and was completed in 2020.
Gas stations
SASCO Station – Medina
Removing the old towers station and building it again for SASCO in Medina, within six months.
Client
Saudi Automotive Services and Equipment Company (SASCO)
sector
Gas stations
City
Madinah
Scope
Remove an old station and build a complete gas station
Status
Completed
Project Overview
SASCO Station - Medina
Completed Scope
Removal of old buildings and facilities
Fuel tanks
Workshop buildings
Car wash
supermarket
Station canopy
Chapel and administration office
Staff housing
Electrical and control rooms
Pavements, asphalt and yard layout
afforestation
Key Construction Stages
Remove the old station
Removing existing buildings and structures and preparing the site for construction.
Infrastructure and reservoirs
Implementing the station’s infrastructure and installing fuel tanks.
Buildings and canopy
Workshops, laundry, supermarket and canopy, with a prayer room, administration office, staff accommodation and electrical and control rooms.
Finishes and squares
Finishes, electromechanical works, advertising boards, then sidewalks, asphalt, planning and landscaping.
Quality and Testing
Testing the tightness of tanks and piping networks
Calibration of filling systems
Testing of fire and safety systems
Checking grounding and lightning rod
Testing the layout of the squares and their inclinations